Greenland Rare Earth Project Hits 13% Concentrate
Early flotation tests lift grade twentyfold but recover only 20.3% of oxides, with Phase 2 aiming to improve results.
Updated on Nov. 3, 2026 in Geology

Arkadian Strategic Metals PLC, majority owner of the Motzfeldt project in Greenland, reported initial rare earth concentrate results from a preliminary flotation test. The test produced a concentrate grading 13.37% total rare earth oxides from a 0.65% starting grade, recovering 20.3% of the oxides. The results are early, research-stage scoping work rather than a production-ready process.
Why it matters
Rare earth supply is a bottleneck for magnets and electronics, and new deposits must show they can be upgraded into saleable concentrate before they matter commercially. These scoping results show the Aries deposit, which hosts an inferred 340 million-tonne resource, can yield a concentrate at this grade, though recovery remains low.
The flotation test lifted total rare earth oxides from 0.65% in the starting material to 13.37% in the concentrate, about a twentyfold upgrade, while recovering 20.3% of the oxides in the feed. Because the run used a single unoptimised stage on one bulk sample, the recovery figure reflects an early baseline rather than a demonstrated plant-scale yield.
The players
Arkadian Strategic Metals PLC
A mineral exploration company that is majority owner of the Motzfeldt rare earth project in Greenland and the Aries deposit.
The details
Flotation is a process that separates minerals by floating selected particles on air bubbles in water, based on surface chemistry. Gravity separation, by contrast, sorts particles by density. Arkadian's mineral analysis indicated that grinding the ore more finely would be the main route to improving recovery, since finer particles liberate more of the rare earth minerals. The scoping tests also produced gravity concentrates carrying rare earths and zirconium.
Timeline
Initial metallurgical test results were published on 3 November 2026.
The Tech Race
The Motzfeldt results are preliminary scoping work, not a demonstrated production process. Phase 2 will aim to raise recovery and concentrate grade, and a second phase will test combined gravity separation and flotation.
For readers, the practical effect is limited to the supply pipeline: rare earths feed magnets and electronics, but this project has not reached production and no availability or pricing timeline has been announced. Results from Phase 2 and the pilot plant work will determine whether the deposit can supply a commercial product.
The takeaway
The key question is whether Phase 2 can lift recovery well above the 20.3% baseline. Watch for the Phase 2 testwork results and the pilot plant gold recovery results from the Clogau-St David's floor material.
What happens next
Phase 2 testwork at the Motzfeldt project is designed to raise recovery and concentrate grade, and a second phase will test combined gravity separation and flotation; the approximately 1.5 tonnes of floor material from Clogau-St David's is scheduled for pilot plant processing to test gold recovery.