Nebius Capacity Delays Push Revenue Into 2027
Power-source delays at a third-party New Jersey site now push the company's connected-power target out of reach on current timing.
Updated on Nov. 16, 2026 in Data Centers

BofA Securities cut its price objective on Nebius to $265 from $310 while keeping its Buy rating, after Nebius cut its 2026 revenue guidance by $100 million to $3.1 billion. The development is a financial-analyst revision to a company with existing public results, so the infrastructure it describes is shipped capacity being delayed rather than announced or research-stage technology.
Why it matters
The delays trace to a reliance on third-party data center capacity, where a power-source transition at Vineland, New Jersey pushed activation and revenue recognition from late 2026 into early 2027. The episode shows how dependence on outside power and facilities can slow the buildout of AI compute capacity even when demand and reported revenue are strong.
Nebius reported Q3 2026 revenue of $980.8 million, up 571% year over year, with an EBITDA margin of 47.5% against a consensus of 39.5%. BofA cut its year-end 2026 active power estimate to 560 MW from 702 MW, and the company no longer expects to reach its 800 MW to 1 GW connected-power target.
The players
Nebius
An AI infrastructure company whose reported Q3 2026 results and 2026 guidance cut are at the center of this story.
BofA Securities
The Bank of America brokerage that cut its Nebius price objective to $265 while keeping a Buy rating.
Citi
The bank that provided a $3.5 billion bridge financing to Nebius in October 2026.
Bloom Energy
A fuel-cell manufacturer whose sustainable fuel cells are replacing the power source at the Vineland, New Jersey site.
The details
Nebius relies in part on third-party data center capacity, and delays at one site pushed when that capacity comes online. The affected facility at Vineland, New Jersey is transitioning its power source to Bloom Energy's sustainable fuel cells, and that transition is what held up activation. Because revenue is recognized only once capacity is live, the slip moved revenue from late 2026 into early 2027. BofA expects the Vineland capacity to be fully live by the second quarter of 2027.
Timeline
Q3 2026: Nebius reported revenue of $980.8 million.
October 2026: Citi provided a $3.5 billion bridge financing.
February 2027: Nebius moved its target of about $7 billion in ARR from December.
Early 2027: Delayed capacity activation and revenue recognition are expected to land.
Q2 2027: BofA expects Vineland capacity to be fully live.
The Tech Race
The delay is a reminder that AI compute providers racing to add capacity depend on third-party power and facilities, not only on their own buildouts. Nebius's target of 800 MW to 1 GW of connected power now sits out of reach on the current schedule, which shows how far execution risk can trail the financing and demand that drive the race.
Customers and partners who depend on Nebius's capacity should expect revenue and activation to slide into early 2027 rather than late 2026. Investors have already reacted, with shares falling 22% after the results, and management expects prepayments and contract-backed financing to fund 75% to 85% of 2027 capex.
The takeaway
The main trajectory signal is that AI compute growth is now gated by power and third-party site readiness as much as by capital and demand. Watch whether the Vineland capacity is fully live by Q2 2027 and whether Nebius reaches the February 2027 target of about $7 billion in ARR.
What happens next
BofA expects the Vineland capacity to be fully live by the second quarter of 2027, and Nebius moved its target of about $7 billion in ARR to February 2027, which are the dated checkpoints to track.