Hyperscaler Lease Adds 150 MW of AI Capacity
The 18-year deal worth about $5.4 billion in base revenue delivers capacity in Louisiana starting in 2028.
Updated on Nov. 23, 2026 in Data Centers

Live Poll
Do you expect your local electricity bills to rise due to new data centers?
Applied Digital signed an 18-year lease for 150 MW of critical IT capacity with a tier-one, investment-grade hyperscaler, which was not named. The lease is an announced commercial agreement, and capacity delivery is expected to begin in the first half of 2028.
Why it matters
The deal extends the company's contracted pipeline for high-density AI infrastructure, with total contracted base-term lease revenue now above $41 billion. It also shows hyperscalers committing to long-term capacity years before it is built, which underpins the buildout of AI data centers.
The figures come from the company's own contract disclosures, with the new lease worth about $5.4 billion over its base term. Against a portfolio of roughly $36.2 billion, the deal raises contracted revenue, though the tenant's identity and the basis for the $12.7 billion renewal-inclusive estimate remain unstated.
The players
Applied Digital
A data center developer building high-power-density, waterless-cooled campuses for AI workloads, with a contracted portfolio of about $36.2 billion across five campuses.
The details
The lease covers 150 megawatts of critical IT capacity, meaning the power available to run servers rather than total facility draw. Applied Digital builds high-power-density facilities designed for AI workloads, which pack more computing hardware into each unit of space and therefore need more power and cooling. The company says these facilities use waterless cooling, a method that avoids consuming large volumes of water for heat removal.
Timeline
May 31, 2026: Contracted portfolio stood at about $36.2 billion across five campuses.
November 23, 2026: Hyperscaler lease and $300 million bridge facility announced.
First half of 2028: Expected start of capacity delivery under the lease.
The Tech Race
Long-dated leases with investment-grade hyperscalers have become the financing basis for AI-focused campuses, and Applied Digital's pipeline is now measured in tens of billions of dollars. The lease's renewal options, which could stretch the term to 33 years, show developers seeking contract durations that match the multi-decade life of the facilities.
The new capacity is not expected to begin delivery until the first half of 2028, so the lease does not change service for users today. Its practical effect is on Louisiana's Delta Forge 1 campus, where the $300 million bridge facility is funding development ahead of that timeline.
The takeaway
Watch whether the first-half 2028 delivery date holds for the 150 MW under lease, since that timing will show whether the build schedule is keeping pace with contracted demand. Track the hyperscaler's identity and any disclosure of the renewal-inclusive $12.7 billion figure in future Applied Digital filings.
Further reading
For more on the buildout behind this lease, explore Data Centers coverage across the region.
Source note: This article includes information reported by Crypto Briefing.
Live Poll
Do you expect your local electricity bills to rise due to new data centers?




