Lowell City Council Halts New Data Center Construction
The 360-day moratorium marks a reversal in city policy regarding large-scale industrial data facilities.
Updated on Oct. 26, 2026 in Data Centers

Live Poll
Do you believe the economic benefits of local data centers justify the impact on residential neighborhoods?
In March 2026, the Lowell City Council implemented a 360-day moratorium on new commercial data center construction amid mounting community friction. This legislative move followed years of debate surrounding the 352,000-square-foot Markley Lowell Data Center facility.
Why it matters
The pause reflects an intensifying conflict between municipal economic development strategies and resident concerns over environmental quality. As data centers scale in energy and infrastructure requirements, cities are re-evaluating long-standing tax incentives and zoning frameworks.
The Markley Lowell Data Center operates with 27 backup diesel generators that perform five-minute weekly tests. These generators emit a measured sound level of 44 decibels.
The players
Markley Lowell Data Center
A large-scale commercial facility occupying 352,000 square feet of industrial space.
Lowell City Council
The municipal legislative body responsible for zoning, tax incentives, and local development policies.
Conservation Law Foundation
An environmental advocacy organization representing residents in legal challenges against industrial expansions.
The details
The facility manages infrastructure across 352,000 square feet, supporting over 100 full-time staff members. Expansion plans previously included increasing the site's generator count to 27, prompting residents to raise alarms regarding potential noise, dust, and cooling tower emissions. A temporary injunction granted in August 2026 has since halted these specific expansion efforts while the litigation proceeds.
Timeline
2015: City council approved a 20-year tax break for Markley.
March 2026: City council unanimously passed a 360-day data center moratorium.
August 2026: Court granted a temporary injunction against data center expansion.
The Tech Race
Lowell is currently navigating the tension between prior industrial redevelopment goals and contemporary quality-of-life standards. The city's moratorium updates the precedent set by the 2015 tax incentive agreement by introducing a temporary halt to further infrastructure growth.
Residents currently experiencing concerns over noise and cooling tower emissions will see a temporary cessation of expansion-related construction activities. The facility's 27 generators remain subject to weekly testing until legal proceedings resolve the expansion's future.
The takeaway
The city’s 360-day pause signifies a shift in how municipalities weigh corporate tax breaks against residential environmental concerns. Observers should track the pending court injunction and the final outcome of the Conservation Law Foundation’s legal challenge for clues on future zoning precedents.
Further reading
For broader trends on infrastructure permitting, visit Data Centers.