We Are the Frontier

Hanford Waste Cleanup Gets New Pretreatment Line

The planned AMPS facility is projected to cut 12 years from East Tank Farm cleanup, though it is still under construction.

Updated on Nov. 2, 2026 in Science

Flat vector editorial illustration of cylindrical steel process vessels and a pipe manifold on a concrete pad beside a crane, set against desert scrubland.
The Department of Energy broke ground on the AMPS pretreatment facility at Hanford on November 2, 2026, to speed cleanup of radioactive tank waste. AI Illustration. Upload story photo >

The Department of Energy broke ground on the Advanced Modular Pretreatment System (AMPS) at the Hanford Nuclear Reservation in Washington state on November 2, 2026. The facility is announced and under construction, not yet operating.

Why it matters

Hanford's liquid radioactive waste must be pretreated before it can be glassified at the Waste Treatment and Immobilization Plant, and that upstream step has been a bottleneck. Adding a dedicated pretreatment line signals the cleanup program is moving to remove that constraint now.

DOE projects AMPS will pretreat 3.6 million gallons of waste per year and remove 99.9 percent of radioactive material before vitrification, compared with the roughly 2 million gallons per year the treatment plant can handle on its own. These are agency projections for a facility that has only just broken ground.

The players

U.S. Department of Energy

The federal agency that manages the Hanford cleanup and announced the AMPS groundbreaking.

Hanford Nuclear Reservation

The former plutonium production site in southeastern Washington state that is now the largest environmental cleanup project in the United States.

The details

Before liquid waste from Hanford's underground tanks can be turned into glass, radioactive materials must be separated out, a step called pretreatment. AMPS will sit beside the AP tank farm in the 200 East Area and remove 99.9 percent of those radioactive materials. The separated waste then moves to the Vitrification (VIT) plant, where it is melted into glass, a stable and inert form suited to long-term storage. Vitrification has been running at the VIT plant for just over a year.

Timeline

  1. November 2, 2026: DOE announces groundbreaking for AMPS at Hanford.

  2. Over the past year: the VIT plant has been vitrifying liquid waste from hundreds of Hanford tanks.

The Tech Race

The Hanford cleanup has relied on vitrification at the Waste Treatment and Immobilization Plant to convert tank waste into glass. AMPS adds a separate pretreatment line so the glass-making step is no longer throttled by upstream separation.

Washington residents near Hanford will see the cleanup timeline shift as AMPS comes online, though no completion date has been given. The immediate change is construction at the 200 East Area, not any change in service.

The takeaway

Watch for AMPS's construction schedule and cost disclosures, which will show whether the three-fold throughput gain and 12-year cleanup reduction hold up. Readers can track Hanford progress through DOE's Office of River Protection updates.

Further reading

For more on how the nation handles radioactive waste, explore our Nuclear coverage.

Source note: This article includes information reported by NEWStalk 870.