Google's $17B Wyoming Campus Brings Own Power
The 716-acre Project Tembo campus is announced, with initial operations targeted for 2028 and full completion in 2031.
Updated on Nov. 5, 2026 in Data Centers

Live Poll
Do you think data centers are improving life in your area?
Google has committed $17 billion to Project Tembo, its first data center campus in Wyoming, on about 716 acres in south Laramie County near Cheyenne. The project is announced, not yet built: site work is expected to begin by late 2026, with initial operations targeted for the second half of 2028.
Why it matters
The campus is designed around 2.7 GW of capacity including reserves, a scale that ties a hyperscale cloud build directly to new power generation. Black Hills Corp.'s $1.8 billion commitment to new generation for the project shows how AI-era data centers are pulling utilities into building dedicated supply.
The announced figures are a 2.7 GW design capacity, including reserves, across four data center buildings totaling about 3.08 million square feet on 716 acres. Those are planned specifications from the project's announcement, and the source does not report measured power draw or delivered capacity.
The players
Alphabet's cloud and AI company, which operates large hyperscale data center networks and is now lead developer of Project Tembo.
Black Hills Corp.
A Rapid City, South Dakota-based utility company that committed $1.8 billion to new generation tied to the Wyoming campus.
The details
Project Tembo is a planned hyperscale campus, a cluster of large data center buildings that house computing equipment for cloud and AI workloads. The campus includes four large data center buildings, an office building, logistics and network facilities, and supporting infrastructure. It is designed as a private microgrid, a localized power system serving a specific customer rather than the wider public grid, which runs through 2048. Black Hills Corp. has committed $1.8 billion to new generation tied to the project.
Timeline
Mid-2026: Google took over as lead of the project through Jupiter Star Holdings LLC after Crusoe exited.
Late 2026: Site work and mass grading are expected to begin.
2027: Vertical construction is slated to begin.
Second half of 2028: Initial operations are targeted.
First half of 2031: Full completion is expected.
The Tech Race
Project Tembo follows the pattern of hyperscale operators locking in dedicated power alongside land and buildings, rather than relying solely on the existing public grid. The project's microgrid running through 2048 places Google's Wyoming campus among the more power-committed builds in the current data center cycle.
Wyoming residents will see the effect mainly through construction employment, with peak needs of about 2,500 workers, and a projected rise in the local tax base. The campus does not provide consumer-facing services, and its timeline runs to a 2028 start of operations and 2031 completion.
The takeaway
Project Tembo shows a hyperscale campus being built with its own generation and microgrid as a core design element. Watch for the start of site work in late 2026, the first construction permits and grading milestones, and whether the 2028 initial-operations target holds.
What happens next
Site work and mass grading are expected to begin by late 2026, with vertical construction slated for 2027.
Further reading
For the broader buildout behind this campus, see Data Centers coverage on how cloud operators are securing power.